RIDGEFIELD — The second phase of the realignment of Main Street is progressing well, according to the town.
Work continues without delays at the CVS parking lot near the Main and Prospect streets intersection. During the week of July 11, Richards Construction will dig three test pits along Main Street for fire hydrant relocation and verification of existing water main conditions.
This work will begin at 7 p.m. in the following locations:
1) the entrance to the CVS parking lot, 2) the intersection of Catoonah and Main Street, and 3) the intersection of Bailey and Main Street.
There will be no significant traffic disruption due to this necessary work, according to the town.
The $4 million project is intended to improve traffic flow on Main Street.
For more information, refer to the Main Street Project Fact Sheet at https://www.ridgefieldct.org/office-first-selectman/pages/main-street-project.
Follow the @TownofRidgefieldCT on Facebook and @CTRidgefield on Twitter for important updates during the next six months.